Amsterdam Data Centres and Grid Congestion: Timeline and Sources, 2019 to 2026Go back

Amsterdam Data Centres and Grid Congestion: Timeline and Sources, 2019 to 2026

Two separate limits apply to new data centres in the Amsterdam area. Planning law decides where one may be built and how much power it may add, and Amsterdam, Haarlemmermeer and the national government each set their own rules. Grid capacity decides whether TenneT and Liander can connect it, and in most of Noord-Holland they have no room for new large users. A project needs both a planning consent and a grid connection, so either limit can stop it. Those rules come from the two municipalities, the national government, the grid operators, the Netherlands Authority for Consumers and Markets (ACM) and the courts, and date from July 2019 to August 2026.

September 23, 2026

by Clay Berndt

Amsterdam

Power

Data Centres

Regulation

Loading...

Timeline

DateBodyDecision or eventSource
12 July 2019Municipalities of Amsterdam and HaarlemmermeerPreparatory decisions (voorbereidingsbesluit) pause new data centres in both municipalities, citing the load on the electricity grid and the use of space. Projects already under way are unaffected.Dutch Data Center Association
24 November 2020Municipality of HaarlemmermeerData centre policy takes effect, with a growth budget to 2030.Lokale regelgeving, CVDR646404
17 December 2020Municipality of AmsterdamAdopts Amsterdam Duurzaam Digitaal, the data centre policy for 2020 to 2030: growth capped at 670 MVA to 2030 and a power usage effectiveness (PUE) below 1.2.DLA Piper
16 February 2022National governmentNine-month pause on new hyperscale data centres (more than 10 hectares and more than 70 MW) outside designated areas, while national rules are drafted.DutchNews
October 2023TenneTThe high-voltage grid in Noord-Holland reaches its maximum capacity for offtake by large users. New and increased connections go on a waiting list.TenneT
December 2023Municipality of AmsterdamA new preparatory decision restricts data centres and announces a temporary stop on new ones until 2030.Dutch Data Center Association, Computable
20 December 2023National governmentDecree amending the Besluit kwaliteit leefomgeving makes the hyperscale restriction permanent, in force 1 January 2024.Staatsblad 2023, 492
16 April 2024ACMCode decision GOTORK, short for gebruik op tijd of raak het kwijt (use it in time or lose it), on unused contracted transport capacity.ACM
October 2024ACMThe prioritisation framework (prioriteringskader) starts to apply: in congestion areas, grid operators may connect certain categories of user ahead of the queue.Binnenlands Bestuur
20 December 2024TenneT and LianderNo extra grid capacity in large parts of Noord-Holland for the next ten years. Overloads are expected from 2026 north of Beverwijk and around the Vijfhuizen high-voltage substation, including south-west Amsterdam. Of 606 large users with connections above 1 MW asked about avoiding the peak, 66 saw a way to do it.TenneT, TenneT newsletter
March 2025Trade and Industry Appeals Tribunal (CBb)Annuls the ACM prioritisation framework for insufficient reasoning (ECLI:NL:CBB:2025:145) and leaves it in force until 1 January 2026 while the ACM decides again.Binnenlands Bestuur
April 2025Municipality of AmsterdamAlderman Zita Pels proposes extending the stop to 2035 and applying it to expansions of existing data centres as well.Computable
11 June 2025Municipality of AmsterdamThe stop on new large data centres applies from this date.Liander
21 November 2025LianderBecause of Amsterdam's data centre policy, three planned substations are no longer needed, saving about €125 million.Liander
12 December 2025ACMReplacement prioritisation framework published, in force 1 January 2026.ACM
15 January 2026LianderRevised expected end dates for congested sub-grids serving Amsterdam.Liander
27 January 2026Minister Mona KeijzerStates that a 78 MW data centre for Microsoft in Amsterdam cannot be stopped because its permit was granted five years earlier.NOS
29 April 2026District court, ArnhemRules for TenneT against Goodman, a developer seeking a 70 MW connection at the Vijfhuizen substation near Schiphol for a data centre. The court finds the grid at full capacity and Goodman stays on the waiting list. NL Times reports that the constraint could last until around 2035.NL Times
2 June 2026Liander27,500 household requests for a heavier connection in January to May 2026, against 18,000 a year earlier; about 7,300 households on a waiting list for the first time.NL Times
1 July 2026Grid operators, national ruleNew or heavier household connections in full areas go on the waiting list. Homes up to 3 x 35 A count as a basic need and get priority.Liander
July 2026Municipality of AmsterdamBuilding permit for an Equinix data centre on the Amstel III business park in Zuidoost: four towers and an 80 MW connection to TenneT's grid. One 60-metre tower is built first on Liander capacity applied for years earlier; the other three wait for TenneT substations expected in 2036.NL Times, DutchNews
18 August 2026Residents, municipality of AmsterdamMore than 500 people have joined the Stop Datacenter Zuidoost campaign against the Equinix permit. The municipality says revoking the permit at this stage would expose it to legal action and penalties.DutchNews

Planning limits in force on 23 September 2026

RuleIssued byApplies toLimit
Data centre policyMunicipality of AmsterdamThe municipality of AmsterdamNo new data centres and no expansions until 2035. Excepted: applications submitted before 28 December 2023, and projects already in advanced talks with the municipality.
Datacenterbeleid gemeente HaarlemmermeerMunicipality of HaarlemmermeerFour designated areas: Polanenpark, Schiphol-Rijk, Corneliahoeve and Schiphol Trade Park750 MVA of added connection capacity to 2030, at most 70 MVA a year, split by area: Polanenpark 100 MVA, Corneliahoeve 100 MVA, Schiphol-Rijk 350 MVA, Schiphol Trade Park 200 MVA. A site above 80 MVA needs its own 150 kV substation. No extra space after 2030. PUE below 1.2 and waste heat offered to district heating where applicable.
Instruction rule for hyperscale data centresNational governmentThe NetherlandsA data centre with more than 10 hectares of built floor area and a connection of 70 MW or more may be built only at designated locations in Het Hogeland and Hollands Kroon.

The national rule applies both tests together, so a building that exceeds only one of them is not a hyperscale data centre in law. According to NOS, the 78 MW Microsoft project in Amsterdam stays under the floor-area test because it is built as three 85-metre towers.

Liander waiting-list estimates for Amsterdam sub-grids, January 2026

Sub-grid (deelnet)Amsterdam requests waitingPrevious estimateEstimate from 15 January 2026Reason given
OostzaanAbout 12020312029 to 2030Demand grew less than forecast
VijfhuizenAbout 8020312036Delay to the new A9-Zuid substation in Haarlemmermeer
Diemen (Amsterdam Zuidoost and Oost)About 150Fourth quarter of 2036End of 2037Delays to new and expanded substations

Source: Liander, 15 January 2026.

In its December 2024 notice, Liander said it would build or expand 42 large and 40 small substations and lay or replace 6,000 km of cable in Noord-Holland by 2033, with extra capacity released in stages from 2031 and the high-voltage expansion complete by 2036 (TenneT).

Allocation rules for congested capacity

Prioritisation framework. In a congestion area, grid operators connect three categories ahead of the queue: congestion relievers (projects that free capacity on the grid, such as batteries), safety (services essential to national security, including hospitals, police and fire services) and basic needs. The replacement framework in force from 1 January 2026 added public transport, shared housing, telecommunications and gas storage to basic needs (ACM). Data centres are not a category of their own. A data centre can be prioritised only through a joint request initiated by a priority party whose data it handles exclusively (NLconnect).

GOTORK. A grid operator may reduce the contracted transport capacity of a user connected at medium, high or extra-high voltage in a congestion area when a substantial amount of it goes unused, and offer the freed capacity to users on the waiting list. The operator must consult the user first, and the user can keep the capacity by showing it is needed now or will be within a reasonable period (ACM).

Terms

  • Grid congestion (netcongestie): the state in which a grid operator cannot contract new or increased transport capacity in an area without risking overload. Existing contracts continue.
  • Contracted transport capacity (gecontracteerd transportvermogen, GTV): the capacity a connected user has agreed with the grid operator, and the quantity that waiting lists and GOTORK act on.
  • TenneT: the operator of the national high-voltage transmission grid.
  • Liander: the regional distribution operator for Noord-Holland, Gelderland, Friesland, Flevoland and parts of Zuid-Holland, including Amsterdam.
  • MVA and MW: the municipal budgets are set in megavolt-amperes of connection capacity, the national rule in megawatts. The two differ by the load's power factor.
  • Preparatory decision (voorbereidingsbesluit): a municipal or national decision under Dutch planning law that temporarily blocks changes of land use while a new plan is prepared.

Revision history

  • 23 September 2026: first published.

Disclosure

Serverside.com, the publisher, rents out dedicated servers housed in a facility in Haarlemmermeer and is affected by the decisions listed here. Our commentary on what the grid situation means for server customers is in a separate article.